Work to be completed in stages through 2009
Prep Stage
Tasks: Remove & Reconstruct Median
Traffic Impacts: Shift traffic to outside edges of Route 1
Estimated Timeframe: December 2006 to February 2007
Major Construction Stages
| |
Stage 1 |
Stage 2 |
Stage 3 |
Final Stage |
| Work Focus |
Reconstruct south side |
Reconstruct north side |
Reconstruct median area |
Cleanup, bridge painting and landscaping |
| Traffic Impacts |
Shift all traffic to the north side of Route 1 |
Shift all traffic to the south side of Route 1 |
Shift traffic to outside edges of Route 1 |
Minimal |
| Estimated Timeframe |
February 2007 to March 2008 |
March 2008 to January 2009 |
February 2009 to September 2009 |
October 2009 to the end of December 2009 |